Apache Cement Factory Project
Date
2019
Category
Supply and Installation
Submit
2019-06-05
Location
Pyi Nyaung, Mandalay Division
* Project Timeline : 2019 ( Within 1 Month)
* Generators (2000kVA x 7 Units) with Synchronizing and Main Synchronizing
Pre-Site Survey

Calculate the complete site survey for customer's satisfaction and provide solutions.

Direct to site or home initial setup is free of charge for specific items.

Maintainance

Support Regular maintenance services, Emergency Troubleshooting/ Fault Finding (On Call) services

Provide Annual Maintenance Contract (AMC) & regular maintenance visits and can choose the level of response time need to suit as per business requirements.

Fully support spare parts for products within and out of warranty period.

Delivery and Installation

Arrange delivery to customer sites within Yangon, Mandalay & Naypyitaw

Equipment & Scope

Supply and Installation

  • Generators (2000kVA x 7 Units) with Synchronizing and Main Synchronizing
  • Synchro Busbar VCB Panel

  • Fuel Piping System (Auto Filling)

  • Hot air duct

  • Exhaust & Foundation

General Information

  • Project Time Line : 2019 (Within 1 Month)
  • Project Type : Factory

  • Developer : Shwe Taung Cement Co.,Ltd

  • Main Contractor : I.E.M Company Limited

  • Consultant : Holtec Engineering Consultant

  • Location : Pyi Nyaung, Mandalay Division

  • Safety : Zero Accidents